/  Advertising   /  GCQ Project Update

GCQ Project Update

Current Project Update at GCQ in Collingwood

The first part of the level 3 pour has been completed with the second part still being formed up. The second part of the pour will most likely proceed next week, with the panels being ready for erection after the second pour has taken place. In addition to this, last week a couple of flights of stairs were also poured to keep up the structure.

Despite stage 4 restrictions, progress is coming along nicely!

GCQ is due to be completed July 2021

The Alpha14 team boasts more than 50 years collective industry experience developing and managing projects, spanning the commercial, industrial, retail, childcare, and residential sectors in some of Melbourne’s most sought-after and inner-city locations.

For more information on our projects, experience, or joint venture and partnerships, contact projects@alpha14.com.au