GCQ Project Update
GCQ Project Update
The Alpha14 Team have had a great couple of weeks at GCQ!
Level 4 was poured last week, we anticipate level 5 to be poured this week and will continue to stay ahead of program.
Citipower also inspected the substation and all requirements have been met, which now means they can book in the fitout works. The ground floor formwork has also been lifted and will be used on the level 6 pour 1 later this week.