GCQ Project Update
Current Project Update at GCQ in Collingwood
The first part of the level 3 pour has been completed with the second part still being formed up. The second part of the pour will most likely proceed next week, with the panels being ready for erection after the second pour has taken place. In addition to this, last week a couple of flights of stairs were also poured to keep up the structure.
Despite stage 4 restrictions, progress is coming along nicely!
GCQ is due to be completed July 2021